Time of retsart
The recovery plan (WAP) runs only when:
- the crisis team has activated the WAP
- the organizational and technical requirements for the WAP are met
The implementation of the restart is regulated separately for the following types of failure.
Failure of buildings
Time-critical organizational units move to designated alternative locations. Employees who are not involved in time-critical business processes are sent home. The backup location starts up and the primary location starts up again via the following WAP:
/BSI-Standard-200-4_Hilfmittel/BSI_Standard_200_4_Hilfmittel.html BSI template recovery plan
IT failure
In the case of complex IT failures, the aim is to fix them as quickly as possible and with the least damage to the company. A comprehensive WAP is available for this purpose:
/BSI-Standard-200-4_Hilfmittel/BSI_Standard_200_4_Hilfmittel.html BSI template recovery plan
Employee absence
A recovery plan is not yet available and is expected to be drawn up by the end of 2023.